OCG23-003 DFO South Wharf Reconfiguration - 公共プロジェクト現場
-
03rd 11月 2023, Site Security
IMPORTANT - PLEASE READ
添付ファイル :
Melbourne Cup Long Weekend - Site Security Safety Bulletin.
OTTO Safety Bulletin - Site Security over the Melbourne Cup Long Weekend 2023.pdf
-
17th 10月 2023, Working at Heights Rescue Plan
Hi All,
添付ファイル :
Please find attached a Working at Heights Rescue Plan document for your reference. It outlines -
- Relevant information to be considered and included in a Working at
Heights Rescue Plan.
- A Rescue Plan Form
- Safety Equipment to be included in a Working at Heights Rescue
Kit.
I have also updated the HSEQ Construction Management Plan document to include this information.
Regards,
Sarah McNair
Office Manager
Working at Heights Rescue Plan.pdf
-
20th 3月 2023, Dtech Concrete Scanning Report
Results from concrete scanning conducted on the ground level and level 1 for steel installation and penos on level 1 at DFO South Wharf on the 20/03/23.
添付ファイル :
CS8754-OTTO CG-DFO SOUTH WHARF REPORT-20MAR23.pdf
現在の現場の天気
利用できません
タイムゾーン - オーストラリア東部標準時
予測 - 日曜日, 1 3月
Showers.
分: 20C マックス: 24C
降雨の可能性: 95%パーセント
予想降雨量: 7 に 30mm
予測場所 - Melbourne, VICTORIA
タイムゾーン - オーストラリア東部標準時
明日 - 月曜日, 2 3月
Shower or two.
分: 19C マックス: 22C
降雨の可能性: 70%パーセント
予想降雨量: 0 に 6mm